NEC3 ECC: Is there a limit on how much Project Manager can delegate?

+1 vote
256 views
How many people can the PM designate to carry out his role at any one time and can delegated personnel sign documents with "PM name" rather than "on behalf of PM name"?
asked Mar 31, 2015 in General by anonymous   11 63 89

1 Answer

+1 vote
 
Best answer
There is no limit stated in the contract as to how many people or what individual duties the PM can delegate to.

IIt is 'intriguing' to put it mildy (or plain wrong to to be more assertive) that people sign a communication with another person's name. This is unnecessary if they are correctly delegated the duties in accordance with clause 14.2 as is signing it  "on behalf of PM name".
answered Mar 31, 2015 by Jon Broome Panel Member (60,890 points)