What happens if the Project Manager does not reply to the Contractor’s notification that he has failed to reply within the time allowed?

What happens if the Project Manager does not reply to the Contractor’s notification that he has failed to reply within the time allowed?

1 Like

If the Project Manager does not reply to the notification within two weeks, and unless the quotation is for a proposed instruction or a proposed changed decision, the Contractor’s notification is treated as acceptance of the quotation by the Project Manager (see clause 62.6).