What happens if the Project Manager does not reply to the Contractor’s notification that he has failed to reply within the time allowed?

+1 vote
330 views
What happens if the Project Manager does not reply to the Contractor’s notification that he has failed to reply within the time allowed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

If the Project Manager does not reply to the notification within two weeks, and unless the quotation is for a proposed instruction or a proposed changed decision, the Contractor’s notification is treated as acceptance of the quotation by the Project Manager (see clause 62.6).

answered Oct 9, 2012 by BuiltIntelligence (870 points)