Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,912 questions

5,237 answers

1,011 comments

Register its Free

Download here

Can you explain to me what is meant by the term Follow-on Action Recommendations in Prince2?

+1 vote
400 views
I am struggling to find this on the web.
asked Mar 27, 2015 in PRINCE2 by anonymous   6 37 56

1 Answer

+1 vote
 
Best answer
Follow-on Action Recommendations. A report that can be used as input to the process of creating a Business Case/Project Mandate for any follow-on PRINCE2 project and for recording any follow-on instructions covering incomplete products or outstanding Project Issues.
answered Mar 27, 2015 by Chris Corr (9,350 points)