Can you explain to me what is meant by the term End Stage Report in Prince2?

+1 vote
362 views
I am struggling to find this on the web.
asked Mar 27, 2015 in PRINCE2 by anonymous   6 37 56

1 Answer

+1 vote
 
Best answer
End Project Report is a report given by the Project Manager to the Project Board that confirms the handover of all products and provides an updated Business Case and an assessment of how well the project has done against its Project Initiation Document.
answered Mar 27, 2015 by Chris Corr (9,350 points)