Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,656 questions

4,934 answers

851 comments

Register its Free

Download here

Can you explain to me what is meant by the term Checkpoint Report in Prince2?

+1 vote
334 views
I am struggling to find this on the web.
asked Mar 27, 2015 in PRINCE2 by anonymous   2 27 40

1 Answer

+1 vote
 
Best answer
Checkpoint Report is a progress report of the information gathered at a checkpoint meeting which is given by a team to the Project Manager and provides reporting data as defined in the Work Package.
answered Mar 27, 2015 by Chris Corr (9,310 points)