Can you explain to me what is meant by the term Checkpoint Report in Prince2?

+1 vote
400 views
I am struggling to find this on the web.
asked Mar 27, 2015 in PRINCE2 by anonymous  

1 Answer

+1 vote
 
Best answer
Checkpoint Report is a progress report of the information gathered at a checkpoint meeting which is given by a team to the Project Manager and provides reporting data as defined in the Work Package.
answered Mar 27, 2015 by Chris Corr (9,410 points)