Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,203 questions

5,564 answers

1,215 comments

Register its Free

Download here

Can you explain to me what is meant by the term Checkpoint Report in Prince2?

+1 vote
376 views
I am struggling to find this on the web.
asked Mar 27, 2015 in PRINCE2 by anonymous   7 48 69

1 Answer

+1 vote
 
Best answer
Checkpoint Report is a progress report of the information gathered at a checkpoint meeting which is given by a team to the Project Manager and provides reporting data as defined in the Work Package.
answered Mar 27, 2015 by Chris Corr (9,400 points)