Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,751 questions

6,168 answers

1,429 comments

Register its Free

Download here

What happens if the Project Manager does not reply to a quotation from the Contractor within the time allowed?

+1 vote
337 views
What happens if the Project Manager does not reply to a quotation from the Contractor within the time allowed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

If the Project Manager does not reply to a quotation within the time allowed, the Contractor may notify the Project Manager to this effect (see clause 62.6).

answered Oct 9, 2012 by BuiltIntelligence (870 points)