What happens if the Project Manager does not reply to a quotation from the Contractor within the time allowed?

+1 vote
324 views
What happens if the Project Manager does not reply to a quotation from the Contractor within the time allowed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

If the Project Manager does not reply to a quotation within the time allowed, the Contractor may notify the Project Manager to this effect (see clause 62.6).

answered Oct 9, 2012 by BuiltIntelligence (870 points)