What must the Contractor state on each programme he submits to the Project Manager for acceptance?

What must the Contractor state on each programme he submits to the Project Manager for acceptance?

On each programme the Contractor submits to the Project Manager he must include:

	for each operation, a statement of how the Contractor plans to do the work identifying the principal Equipment and other resources which he plans to use and

	other information which the Works Information requires the Contractor to show on a programme submitted for acceptance (see Clause 31.2).