Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,868 questions

6,316 answers

1,502 comments

Register its Free

Download here

How long does the Contractor have to submit a revised quotation for dealing with a compensation event?

+1 vote
350 views
How long does the Contractor have to submit a revised quotation for dealing with a compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Contractor submits the revised quotation within three weeks of being instructed to do so by the Project Manager (see clause 62.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)