How long does the Contractor have to submit a revised quotation for dealing with a compensation event?

+1 vote
339 views
How long does the Contractor have to submit a revised quotation for dealing with a compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Contractor submits the revised quotation within three weeks of being instructed to do so by the Project Manager (see clause 62.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)