Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,755 questions

6,176 answers

1,431 comments

Register its Free

Download here

What must the Project Manager do before instructing the Contractor to submit a revised quotation for dealing with a compensation event?

+1 vote
359 views

What must the Project Manager do before instructing the Contractor to submit a revised quotation for dealing with a compensation event?                                                  

asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Before instructing the Contractor to submit a revised quotation, the Project Manager must explain his reasons for doing so (see clause 62.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)