What must the Project Manager do before instructing the Contractor to submit a revised quotation for dealing with a compensation event?

+1 vote
353 views

What must the Project Manager do before instructing the Contractor to submit a revised quotation for dealing with a compensation event?                                                  

asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Before instructing the Contractor to submit a revised quotation, the Project Manager must explain his reasons for doing so (see clause 62.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)