What are the four possible categories of reply by the Project Manager to the Contractor’s quotation for dealing with a compensation event?

+1 vote
333 views
What are the four possible categories of reply by the Project Manager to the Contractor’s quotation for dealing with a compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Project Manager’s reply is either:

  • an instruction to submit a revised quotation,
  • an acceptance of a quotation,
  • a notification that a proposed instruction will not be given or a proposed changed decision will not be made or
  • a notification that he will be making his own decision (see clause 62.3).
answered Oct 9, 2012 by BuiltIntelligence (870 points)