Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,496 questions

5,898 answers

1,321 comments

Register its Free

Download here

How long does the Project Manager have to reply to the Contractor’s quotation for dealing with a compensation event?

+1 vote
338 views
How long does the Project Manager have to reply to the Contractor’s quotation for dealing with a compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer
The Project Manager replies within two weeks of the Contractor’s submission (see clause 62.3).
answered Oct 9, 2012 by BuiltIntelligence (870 points)