Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,311 questions

4,511 answers

592 comments

34,773 users

Register its Free

Download here

Underestimated costs in tender through life of contract

+1 vote
481 views
A subcontractor has come to a main contractor 2 months before their part of a contract is complete and requested departure from original estimate as they require more money to complete on time. Where would the main contractor stand legally?
asked Jan 5, 2015 in JCT Contracts by james an inquisitive student  
   

1 Answer

+1 vote
Under contract law, it is tough on the subcontractor : they should have got their original estimate and hence offer correct !

This assumes there are no Contractor owned risks (i.e. claims and variations) which have caused the increase in Subcontractor costs. If there are, then the Subcontractor could make a claim under the contract.
answered Jan 5, 2015 by Jon Broome (25,100 points)  
A lump sum contract means, as Jon says, that it is tough on the subcontractor. The same rates are used with variations whether they are too high or too low.

Departures can sometimes be agreed as a variation to the contract where there are other benefits like being able to finish at all. More money might be available if the main contractor wants the subcontractor to accelerate completion (which is currently in delay). But don't bet on it!