Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,330 questions

4,532 answers

596 comments

34,874 users

Register its Free

Download here

NEC3 ECC delay: Contractor delay followed by Employer delay

+1 vote
663 views
If the Contractor was in delay by 4 weeks and the Employer then changed the Works Information during this delay (i.e. after the Contractors delay) resulting in a critical delay of an additional week, is the Contractor able to move the Completion Date out by 5 weeks?
asked Dec 9, 2014 in NEC3 Time by Declan   1
   

1 Answer

+1 vote
I am afraid not (assuming you are talking as the Contractor). The Contractor delay has moved planned Completion by four weeks. The Employer delay then moves planned Completion by one week, and following the rules of clause 63.3 Completion Date would only move by one week.

If you did (or could have) mitigated the initial Contractor delay before the Employer delay came along then yes you would be entitled to a five week delay to planned Completion/Completion Date. This all assumes you also have a regular Accepted Programme for both Parties to call upon to assess any delays with.
answered Dec 9, 2014 by Glenn Hide (33,670 points)