What if the programme for remaining work is altered by the compensation event?

+1 vote
325 views
What if the programme for remaining work is altered by the compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (840 points)  

1 Answer

0 votes
 
Best answer

The Contractor will include the alterations to the Accepted Programme in his quotation (see clause 62.2).

 

answered Oct 9, 2012 by BuiltIntelligence (840 points)