Of what are quotations for compensation events comprised?

+1 vote
376 views

Of what are quotations for compensation events comprised?         

asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Quotations for compensation events comprise proposed changes to the Prices and any delay to the Completion Date and Key Dates assessed by the Contractor (see clause 62.2).

answered Oct 9, 2012 by BuiltIntelligence (870 points)