Before the Contractor submits quotations for other methods of dealing with a compensation event, what is required of the Project Manager?

+1 vote
321 views
Before the Contractor submits quotations for other methods of dealing with a compensation event, what is required of the Project Manager?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Project Manager is required to discuss possible ways of dealing with the event with the Contractor before instructing him to submit quotations. This is intended to avoid wasting the Contractor’s resources in preparing quotations for methods which are not practicable (see clause 62.1).

answered Oct 9, 2012 by BuiltIntelligence (870 points)