Can a compensation event be notified after the defects date?

+1 vote
930 views
Can a compensation event be notified after the defects date?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer
No, a compensation event is not notified after the defects date (see clause 61.7).
answered Oct 9, 2012 by BuiltIntelligence (870 points)