Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,751 questions

6,168 answers

1,429 comments

Register its Free

Download here

What should the Project Manager include in his instruction to submit quotations for a compensation event?

+1 vote
324 views
What should the Project Manager include in his instruction to submit quotations for a compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Project Manager should include his decision on whether or not the Contractor gave an early warning which an experienced contractor could have given. This affects the assessment of the event (see Clause 61.5).

answered Oct 9, 2012 by BuiltIntelligence (870 points)