What should the Project Manager include in his instruction to submit quotations for a compensation event?

+1 vote
318 views
What should the Project Manager include in his instruction to submit quotations for a compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Project Manager should include his decision on whether or not the Contractor gave an early warning which an experienced contractor could have given. This affects the assessment of the event (see Clause 61.5).

answered Oct 9, 2012 by BuiltIntelligence (870 points)