If a contractor is in a pain position (price for works done to date in excess of the target cost) and in delay (with X7 delay damages), do you:
Calculate the pain share using the price for works done to date including the delay damages deduction?
Or;
Calculate the pain share using the price for works done to date excluding any delay damages. Deduct the generated pain sum from the price for works done to date. Then as a separate exercise, further deduct delay damages.