Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,327 questions

5,703 answers

1,262 comments

Register its Free

Download here

What if the Project Manager does not notify the Contractor of his decision regarding the compensation event within two weeks (or a longer period to which the Contractor has agreed)?

+1 vote
344 views
What if the Project Manager does not notify the Contractor of his decision regarding the compensation event within two weeks (or a longer period to which the Contractor has agreed)?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Contractor should notify the Project Manager of his late decision and if the Project Manager fails to respond to his reminder within two weeks, it is treated as acceptance by the Project Manager that the event is a compensation event and an instruction to submit quotations  (see Clause 61.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)  
edited Oct 30, 2012 by Chris Corr