What happens if the Project Manager decides that the event fails any one of these tests?

+1 vote
340 views
What happens if the Project Manager decides that the event fails any one of these tests?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Project Manager notifies the Contractor and no further action is required unless the Contractor disputes the decision and refers it to the Adjudicator (see Clause 61.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)