What happens if the Project Manager decides that the event fails any one of these tests?

+1 vote
331 views
What happens if the Project Manager decides that the event fails any one of these tests?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (840 points)  

1 Answer

0 votes
 
Best answer

The Project Manager notifies the Contractor and no further action is required unless the Contractor disputes the decision and refers it to the Adjudicator (see Clause 61.4).