Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,761 questions

6,181 answers

1,431 comments

Register its Free

Download here

What 4 tests does the Project Manager apply to a compensation event notified by the Contractor in order to decide whether or not to instruct the Contractor to submit quotations for its effect?

+1 vote
420 views
What 4 tests does the Project Manager apply to a compensation event notified by the Contractor in order to decide whether or not to instruct the Contractor to submit quotations for its effect?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The event: has arisen from a fault of the Contractor; has not happened and is not expected to happen; Has no effect on Defined Cost, Completion or meeting a Key Date; Is not one of the compensation events stated in this contract (see Clause 61.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)