Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,598 questions

6,007 answers

1,384 comments

Register its Free

Download here

If the Project Manager has failed to notify the Contractor of a compensation event, what should the Contractor do?

+1 vote
342 views
If the Project Manager has failed to notify the Contractor of a compensation event, what should the Contractor do?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Contractor should notify the Project Manager of the event (see Clause 61.3).

 

answered Oct 9, 2012 by BuiltIntelligence (870 points)