If the Project Manager has failed to notify the Contractor of a compensation event, what should the Contractor do?

+1 vote
337 views
If the Project Manager has failed to notify the Contractor of a compensation event, what should the Contractor do?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Contractor should notify the Project Manager of the event (see Clause 61.3).

 