When should the Contractor be notified of a compensation event which arises from the Project Manager giving an instruction or changing an earlier decision?

When should the Contractor be notified of a compensation event which arises from the Project Manager giving an instruction or changing an earlier decision?

1 Like

The Project Manager should notify the Contractor of the compensation event at the time of giving the instruction or changing the earlier decision. He should also instruct the Contractor to submit quotations (see Clause 61.1).