Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,337 questions

5,718 answers

1,266 comments

Register its Free

Download here

In judging the physical conditions for the purpose of assessing a compensation event, what is the Contractor assumed to have taken into account?

+1 vote
316 views
In judging the physical conditions for the purpose of assessing a compensation event, what is the Contractor assumed to have taken into account?
asked Oct 9, 2012 in NEC3 and NEC4 Contracts by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer
The Site Information; publicly available information referred to in the Site Information; information obtainable from a visual inspection of the site and other information which an experienced contractor could reasonably be expected to have or obtain (see Clause 60.2).
answered Oct 9, 2012 by BuiltIntelligence (870 points)