In judging the physical conditions for the purpose of assessing a compensation event, what is the Contractor assumed to have taken into account?

+1 vote
334 views
In judging the physical conditions for the purpose of assessing a compensation event, what is the Contractor assumed to have taken into account?
asked Oct 9, 2012 in NEC3 and NEC4 Contracts by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer
The Site Information; publicly available information referred to in the Site Information; information obtainable from a visual inspection of the site and other information which an experienced contractor could reasonably be expected to have or obtain (see Clause 60.2).
answered Oct 9, 2012 by BuiltIntelligence (870 points)