Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,366 questions

5,756 answers

1,276 comments

Register its Free

Download here

What are compensation events?

+2 votes
338 views
What are compensation events?
asked Oct 8, 2012 in Compensation Events by BuiltIntelligence (870 points)  
recategorized Oct 23, 2012 by Rob Glasspool

1 Answer

+1 vote
 
Best answer
They are events which affect Prices, the Completion Date or a Key Date and do not arise from the Contractor’s fault. These events entitle the Contractor to be compensated. A list of compensation events is in core Clause 60.1.
answered Oct 8, 2012 by BuiltIntelligence (870 points)