Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,311 questions

4,511 answers

592 comments

34,773 users

Register its Free

Download here

Do late adjudication decisions retain validity?

0 votes
442 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
All decisions are supposed to be reported within a 28 day period. While there may be a little leeway for some delay, this should not be undue and decisions must be delivered with the greatest amount of practicable speed if they overshoot this 28 day period.
answered Feb 6, 2013 by JCT Experts (-20 points)