Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,310 questions

4,511 answers

592 comments

34,766 users

Register its Free

Download here

Is it legally permissible for an adjudicator to make a decision regarding an interim payment should it be the case that the final account value is the issue being referred?

0 votes
272 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
No, as an adjudicator is only entitled, and only has the power, to consider the issue that has been referred.
answered Feb 6, 2013 by JCT Experts (-20 points)