With regards to adjudication, are the various time periods of significance?

0 votes
253 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
Yes, in fact there is a very strict timetable regarding adjudication that must be obeyed. The basic time periods involved in adjudication are covered by the Housing Grants, Construction and Regeneration Act 1996, but the Scheme for Construction Contracts (England and Wales) Regulations 1998 may add additional time to the timetable.
answered Feb 6, 2013 by JCT Experts (-20 points)