If an adjudicator is appointed without the approval of the employer, does the employer have any recourse?

0 votes
253 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
Providing that the adjudicator has been appointed in accordance with the strict legislative procedure that has been laid down explicitly, then there is nothing the employer can do about the appointment of an adjudicator.
answered Feb 6, 2013 by JCT Experts (-20 points)