Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,311 questions

4,511 answers

592 comments

34,773 users

Register its Free

Download here

After termination, is the contractor entitled to a certificate of practical completion?

0 votes
289 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
No, this will be issued to whichever contractor takes over the work, if any.
answered Feb 6, 2013 by JCT Experts (-20 points)