Is it legally valid to claim increased costs by referring to national indices?

0 votes
181 views
asked Feb 5, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
No. In a claim for costs the onus is on the contractor to demonstrate that the increase in costs has been the direct consequence of the incidents cited by the contractor, and there is also a legal requirement to calculate the precise amount of loss and expense.