Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,311 questions

4,511 answers

592 comments

34,773 users

Register its Free

Download here

Why is it problematical to launch a successful claim for overheads and profit?

0 votes
208 views
asked Feb 5, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
This is because in order to make a claim involving either of these elements it is necessary to identify the specific amounts that were actually involved, and avoid all theoretical and / or assumed levels. This can be logistically very difficult to accomplish.
answered Feb 5, 2013 by JCT Experts (-20 points)