If a contractor is instructed to 'complete the design', is it reasonable to assume that the existing design is correct?

This is dependent upon the type of contract that is being utilised. The case Co-operative Insurance Society Ltd v Henry Boot Scotland Ltd (2002) established that the contractor’s obligation under a CDP supplement include an obligation to ensure that the design involved is appropriate and competent. The contractor is not permitted to simply assume that this is the case.