The Contractor has insured a risk which the Employer was contractually obliged to insure but did not. Who pays the cost of this insurance?

The Contractor has insured a risk which the Employer was contractually obliged to insure but did not. Who pays the cost of this insurance?

1 Like

The Employer will pay this cost, as stated in Clause 87.3.