If the Employer decides to insure a risk which the Contractor was required to insure but did not, who pays the cost of the insurance?

+1 vote
362 views

If the Employer decides to insure a risk which the Contractor was required to insure but did not, who pays the cost of the insurance?

asked Oct 11, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

 The Contractor (see Clause 86.1).

answered Oct 11, 2012 by BuiltIntelligence (870 points)  
edited Nov 9, 2012 by Rob Glasspool