What happens if the Contractor has not submitted a required insurance certificate to the Project Manager?

+1 vote
375 views

 What happens if the Contractor has not submitted a required insurance certificate to the Project Manager?

asked Oct 11, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Employer may insure the risk and the cost of the premiums will be paid by the Contractor (see Clause 86.1).

answered Oct 11, 2012 by BuiltIntelligence (870 points)  
edited Nov 9, 2012 by Rob Glasspool