Are there any exceptions to the waiver of subrogation rights?

+1 vote
451 views

Are there any exceptions to the waiver of subrogation rights?

asked Oct 11, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Yes. Instances of fraud are the only exception to the waiver of subrogation rights (see Clause 85.2).

answered Oct 11, 2012 by BuiltIntelligence (870 points)  
edited Nov 9, 2012 by Rob Glasspool