Who bears the cost of an event which is at the Contractor’s risk, if the amount recovered from the insurer does not cover the whole cost of the event?

+1 vote
389 views

Who bears the cost of an event which is at the Contractor’s risk, if the amount recovered from the insurer does not cover the whole cost of the event?

asked Oct 11, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Contractor bears the cost of an amount not recovered from an insurer for events which are at the Contractor’s risk (see Clause 85.4).

answered Oct 11, 2012 by BuiltIntelligence (870 points)