When should the Contractor submit to the Project Manager certificates proving that the insurance required by the contract is in force?

+1 vote
339 views

When should the Contractor submit to the Project Manager certificates proving that the insurance required by the contract is in force?

asked Oct 11, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Before the starting date and on each renewal date of the insurance policy until the defects date (see Clause 85.1).

answered Oct 11, 2012 by BuiltIntelligence (870 points)  
edited Nov 9, 2012 by Rob Glasspool