Does the Contractor have to provide insurance cover for loss of or damage to Equipment?

+1 vote
352 views

Does the Contractor have to provide insurance cover for loss of or damage to Equipment?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Yes. Loss of or damage to Equipment is included in the Insurance Table (see Clause 84.2).

answered Oct 10, 2012 by BuiltIntelligence (870 points)