What is the minimum amount of cover or minimum level of indemnity the Contractor has to provide for loss of or damage to the works, Plant and Materials?

+1 vote
336 views

What is the minimum amount of cover or minimum level of indemnity the Contractor has to provide for loss of or damage to the works, Plant and Materials?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Contractor has to provide insurance cover for the replacement cost, including the amount stated in the Contract Data for the replacement of any Plant and Materials provided by the Employer (see Clause 84.2).

answered Oct 10, 2012 by BuiltIntelligence (870 points)