Are there any circumstances under which a deadline for a tender may be extended?

0 votes
361 views
asked Jan 18, 2013 in Legal and Disputes by Legal Expert (950 points)  

1 Answer

0 votes
 
Best answer
Yes, although deadlines may only be extended in exceptional circumstances. For example, in one case one of the tenderers had suffered a power failure out of its control so the local authority extended the deadline.
answered Jan 18, 2013 by Legal Expert (950 points)