Does the Contractor have to provide insurance cover for loss of or damage to the works, Plant and Materials?

+1 vote
370 views

Does the Contractor have to provide insurance cover for loss of or damage to the works, Plant and Materials?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Yes. Loss of or damage to the works, Plant and Materials is included in the Insurance Table (see Clause 84.2).

answered Oct 10, 2012 by BuiltIntelligence (870 points)