Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,761 questions

6,181 answers

1,431 comments

Register its Free

Download here

Who takes on the risks in the Insurance Table once the works are taken over?

+1 vote
342 views

Who takes on the risks in the Insurance Table once the works are taken over?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Employer assumes the risks in the Insurance Table once the works have been taken over (see Clause 84.2).

answered Oct 10, 2012 by BuiltIntelligence (870 points)